Project management · Free online course
Primavera P6 Planning and Scheduling for Engineers
Plan, schedule and control EPC and construction work in Oracle Primavera P6 Professional: CPM by hand, EPS and WBS, calendars, activities, relationships and lags, constraints, the critical path and float, layouts and printing, resources and levelling, cost loading and cash flow, baselines and progress updates, earned value, DCMA 14-point checks, XER exchange and the basics of delay analysis.
- 14 modules
- 10h 25m of video
- Beginner
- English
- ₹0, free

₹0Free for good
Worth ₹5,999 by length and depth against classroom training. It has always been free; that is not a former price.
No card. Checkout takes a minute and gives you a receipt.
Certificate ₹499, optional. The course is free either way.
Overview
About Primavera P6 Planning and Scheduling for Engineers
Learn project planning with Primavera P6: build a schedule, find the critical path, load resources and update progress.
Primavera P6 Planning and Scheduling for Engineers is a free, self-paced online course from EDWartens for civil, mechanical and electrical engineers moving into planning and project controls, site engineers who update programmes, and graduates seeking planning engineer roles on construction, oil and gas, water and power projects. It has 14 modules and 10h 25m of video lessons, with written notes, a practice task per module, a practical project and a final assessment of 15 questions (pass mark 60%). Learning costs nothing and needs only a free account. The optional EDWartens Certificate of Completion, verifiable by code, is a one-off ₹499 inclusive of GST for learners in India; it is not a vendor credential. Updated 1 November 2026.
Who it is for: Civil, mechanical and electrical engineers moving into planning and project controls, site engineers who update programmes, and graduates seeking planning engineer roles on construction, oil and gas, water and power projects
This course includes
- 10h 25m of video lessons
- 14 modules with written notes and diagrams
- One final assessment: 15 questions, pass mark 60%
- Ask-an-engineer support from practising engineers
- Lifetime access, the course does not expire
- Optional verifiable certificate when you finish
- Step 1 of 3
Learn the 14 modules
10h 25m of video lessons, written notes and a practice task per module, at your own pace.
- Step 2 of 3
Pass the final assessment
15 questions drawn from every module, pass mark 60%, 3 attempts.
- Step 3 of 3
Take the certificate, if you want it
Optional, paid once, only if you choose it. The course stays free either way.
See the certificate and its price
A look inside



From the lessons

The planner's job and CPM by hand
by TechnoCivil

Project set-up: calendars and the WBS
by TechnoCivil

Relationships, lags and constraints
by TechnoCivil

Layouts, filters, grouping and printing
by Phil Hirst

Costs: budgets, expenses, cost loading and cash flow
by TechnoCivil

Earned value from a P6 schedule
by TechnoCivil
Lesson frames belong to the creators named in the Credits and are shown from YouTube.
What you learn
What you will be able to do
By the end you will be able to:
- Calculate a critical path by hand
- Set up a project in P6 with a WBS, calendars and activities
- Link activities and read total float and the longest path
- Load resources and costs and produce an S-curve
- Baseline and update a schedule, then run the DCMA 14-point checks
How it works
How this course works
Watch the lessons
Short video lessons, one module at a time, at your own pace.
Read the notes
Open the Reading tab for the written notes and diagrams of the module.
Check yourself
Answer the questions to see what stuck before you move on.
Final assessment
Pass the final once you have been through the modules.
Certificate, if you want oneOptional
Optional, with a page anyone can use to verify it.
Syllabus
Course content, module by module
In order, at whatever pace suits you. Each module ends with a practice task that builds on the last.
- Modules
- 14
- Video lessons
- 55
- Of video
- 10h 25m
- Final questions
- 15
- 01
The planner's job and CPM by hand
4 lessons · 34m - 02
Getting P6: licences, the workspace, EPS and OBS
5 lessons · 41m - 03
Project set-up: calendars and the WBS
5 lessons · 55m - 04
Activities: types, durations, codes and steps
5 lessons · 1h 4m - 05
Relationships, lags and constraints
5 lessons · 59m - 06
Scheduling: the critical path, float and the longest path
4 lessons · 31m - 07
Layouts, filters, grouping and printing
2 lessons · 37m - 08
Resources and roles: loading, histograms and levelling
5 lessons · 1h 9m Final assessment · 15 questions, pass mark 60%
Project
The course project
Optional practice that ends in the kind of job the course prepares you for, with the documents that go with it.
About 10 hours
Planning a booster pump station: baseline, cost loading, schedule risk, a time impact analysis and a progress report
Plan and control a small EPC job the way a contractor's planning engineer does. Build the baseline programme and prove it by hand, cost-load it, list the schedule risks, measure an employer's change with a time impact analysis, and report period 3 with earned value. The sample pack shows each document for the course's PS-01 pump station.
- 5documents in the pack
- 6steps to follow
- 6things to hand in
- 10 hof work, at your pace
Sample document pack, 5 documents, filled in for the scenario
- PlanPlanning basis: PS-01 booster pump station
- RegisterBaseline programme BL0: logic, dates, float and planned value
- Risk registerSchedule risk register: PS-01
- Change noticeTime impact analysis: the Engineer's instruction for revised pump bases
- ReportProgress report: period 3, data date day 45
Read inside the course and download as a workbook. The project is optional practice, marked when you submit it; the certificate needs only the modules and the final assessment.
Tools
Software, hardware and lessons
Software
Oracle Primavera P6 Professional if your employer or college licenses it. Oracle has no free edition, and a trial, where Oracle offers one, is for evaluation (read its terms), so every exercise can also be done in ProjectLibre, which is free and open source, or by hand in a spreadsheet.
Hardware
A 64-bit Windows PC for P6 Professional (Oracle's list names Windows 11; check the tested configurations for your release). Oracle's stated minimum is 4 GB of memory and 5 GB of disk. ProjectLibre also runs on macOS and Linux.
Who it is for
Beginner to intermediate. For civil, mechanical and electrical engineers moving into planning and project controls, and site engineers asked to update the programme. Basic arithmetic and a spreadsheet are enough; no planning experience is needed. Project Management for Engineers covers the wider project management theory and is a good companion.
Video lessons by
- TechnoCivil
- Phil Hirst
- Plan Academy Inc.
- Global Project Control
- Engineer4Free
- Obalim | Ciel Consulting
- Claims Village
- Learn with EngrWaqas
Independent creators, credited in full under Credits.
Software you need
What to download, where from, what it costs and how to install it. Every link goes to the maker's own site, never a mirror.
Nothing to install if your employer or college gives you Primavera P6 Professional
Otherwise use ProjectLibre Desktop, which is free, or a spreadsheet: every exercise works in either. Oracle's P6 trial is for evaluation only and its terms exclude third-party training, so do not install it for this course.
Optional
Useful, not needed to finish the course.
- 01Free
ProjectLibre Desktop
ProjectLibre
- Runs on
- Windows, macOS and Linux
- Account
- None needed
ProjectLibre Desktop is free and open-source project scheduling software with no subscription. It opens Microsoft Project .mpp files and can import Primavera P6 files. The separate ProjectLibre Cloud product for teams is paid.
Steps
- 1.Open the ProjectLibre Desktop page.
- 2.Select Download ProjectLibre Free; the file downloads from ProjectLibre's SourceForge project.
- 3.Run the installer for your operating system.
- 4.Start ProjectLibre and create a new project, or open the course's .mpp file.
- 5.Build the task list, links and resources, then view the Gantt chart and critical path.
- Use it to practise the scheduling ideas from Microsoft Project or Primavera P6 lessons; menus and some features differ.
Official download pageprojectlibre.com - 02Free
LibreOffice
The Document Foundation
- Runs on
- Windows 10 or 11, macOS 11 or newer (Intel or Apple silicon), Linux
- Account
- None needed
- Size
- up to 1.5 GB of disk space on Windows
LibreOffice is free, open-source software under the Mozilla Public License 2.0, for any use including business. Calc is its spreadsheet.
Steps
- 1.Open the LibreOffice download page.
- 2.Check the page has picked your operating system, then select Download.
- 3.Run the installer (administrator rights are needed on Windows).
- 4.Start LibreOffice Calc for spreadsheet work.
- 5.Save as .xlsx if you need to share files with Excel users.
- Choose the latest main version unless your organisation asks for the older, more conservative release.
Official download pagelibreoffice.org
Checked against each maker's own page on 27 September 2026. Trial lengths and editions change; the maker's page is the final word.
What you walk away with
Your certificate for Primavera P6 Planning and Scheduling for Engineers
Finish the course, pass the final, and this is the document with your name on it.

Verifiable by anyone
Adds to LinkedIn in one click
QR code on the certificate
Names what you can do
A permanent link
Earned, not attended
Learning is free. The certificate is optional.
Add it now and pay only when you have finished the course, or come back for it later. One-off, US$23.99, with a receipt.
Issued by Wartens Ltd (England and Wales, company no. 15262249) through the EDWartens training portal, as a Certificate of Completion for this self-paced course. Sold in India by Wartens Automation Private Limited. It is not a vendor certification, a university award or a CPD-accredited activity, and it does not certify competence on live equipment. Delivered electronically; see the refund policy.
Why learn with EDWartens
What you get with this course.
- Free from the first lesson to the final assessment.
- Video lessons with written notes and a project.
- An optional certificate that anyone can verify online.
FAQ
Common questions
Who is this Primavera P6 course for?
It is for civil, mechanical and electrical engineers moving into planning and project controls, and site engineers asked to update the programme. It also suits graduates who want a planning engineer role on construction, oil and gas, water or power projects. No planning experience is needed. Basic arithmetic and a spreadsheet are enough.
Is this an Oracle Primavera certification?
No. It is not an Oracle certification and does not lead to any Oracle credential. It uses lessons that TechnoCivil, Phil Hirst, Plan Academy Inc. and other educators publish free on YouTube, credited on each module. Oracle, Primavera and P6 are trademarks of Oracle, which is not affiliated with EDWartens.
Do I need a Primavera P6 licence?
No. P6 Professional has no free edition, so use it if your employer or college gives you a licence. Oracle's trial, where it is offered, is for evaluating the software and has its own terms, so do not install it for this course unless you have read them. Every exercise also works in ProjectLibre, which is free and open source, or by hand in a spreadsheet.
Is the course free to learn?
Yes. Every module, the notes, the worked problems, the project and the final assessment are free to learn. The certificate is optional.
Does it cover delay analysis and extension of time claims?
Yes, at the level planning interviews and site work expect. That means fragnets, time impact analysis, windows analysis, the SCL Delay and Disruption Protocol and the FIDIC 2017 notice rules. A live claim still needs the contract in force. When the stakes are high, it needs an experienced delay analyst.
Will it help me get a planning engineer job?
P6 is the scheduling tool most planning job adverts name. That is especially so on large building, infrastructure, oil and gas and power projects in the Middle East and elsewhere. Employers test the method as much as the software. The course drills CPM by hand, float, updating, earned value and the DCMA checks that interviews ask about. The project gives you a sample planning pack to discuss.
How long does the Primavera P6 Planning and Scheduling for Engineers course take?
About 17 hours of video, notes and practice at your own pace. About 10.5 hours of that is video. The optional project takes about 10 hours more.
What certificate does the Primavera P6 Planning and Scheduling for Engineers course give?
An EDWartens certificate of completion, issued when you finish the modules and pass the 15-question final at 60 percent, with a number anyone can verify on our site. It is not an Oracle certification.
What is the project in the Primavera P6 Planning and Scheduling for Engineers course?
You are the contractor's planning engineer for a booster pump station near Sohar, Oman. You produce a planning basis and a baseline programme proved by hand and checked against the DCMA points. You also produce a cost-loaded S-curve, a schedule risk register and a time impact analysis of an employer's change. The last piece is a period 3 progress report with earned value. A complete sample pack shows each document.
Is the Primavera P6 Planning and Scheduling for Engineers course free in India, and what does the certificate cost?
Yes. Learning costs ₹0 in India: every module, the written notes, the practice tasks and the final assessment, with no card and no trial period. The only paid item is the optional EDWartens Certificate of Completion, ₹499 including GST for this beginner course, paid in rupees through Razorpay, and only if you want it after passing the final assessment.
What topics does the Primavera P6 Planning and Scheduling for Engineers course cover, module by module?
The Primavera P6 Planning and Scheduling for Engineers course has 14 modules. It opens with "The planner's job and CPM by hand", goes through "Getting P6: licences, the workspace, EPS and OBS", "Scheduling: the critical path, float and the longest path", "Costs: budgets, expenses, cost loading and cash flow" and "Delay analysis basics: fragnets, TIA and extension of time" and ends with "Final assessment". The full list with minutes is under "What you learn" on this page.
What can I do after the Primavera P6 Planning and Scheduling for Engineers course?
After the Primavera P6 Planning and Scheduling for Engineers course: Calculate the critical path, total float and free float by hand with a forward and backward pass; Set up an EPS, OBS, calendars and a deliverable-based WBS in Primavera P6; Build activities, relationships and lags, and use constraints only where a real date demands one. These are the practical outcomes the course is written around, and the final assessment of 15 questions checks them.
What software and hardware do I need for the Primavera P6 Planning and Scheduling for Engineers course, and does it cost anything?
For the Primavera P6 Planning and Scheduling for Engineers course, software: Oracle Primavera P6 Professional if your employer or college licenses it. Oracle has no free edition, and a trial, where Oracle offers one, is for evaluation (read its terms), so every exercise can also be done in ProjectLibre, which is free and open source, or by hand in a spreadsheet. Hardware: A 64-bit Windows PC for P6 Professional (Oracle's list names Windows 11; check the tested configurations for your release). Oracle's stated minimum is 4 GB of memory and 5 GB of disk. ProjectLibre also runs on macOS and Linux. The course itself is free.
Is the Primavera P6 Planning and Scheduling for Engineers course suitable for me, and what level is it?
Primavera P6 Planning and Scheduling for Engineers is rated beginner. Beginner to intermediate. For civil, mechanical and electrical engineers moving into planning and project controls, and site engineers asked to update the programme. Basic arithmetic and a spreadsheet are enough; no planning experience is needed. Project Management for Engineers covers the wider project management theory and is a good companion. It is written for civil, mechanical and electrical engineers moving into planning and project controls, site engineers who update programmes, and graduates seeking planning engineer roles on construction, oil and gas, water and power projects, and has 10h 25m of video lessons at your own pace.
Which jobs use the skills from the Primavera P6 Planning and Scheduling for Engineers course?
Skills from the Primavera P6 Planning and Scheduling for Engineers course (for example: calculate the critical path, total float and free float by hand with a forward and backward pass) are used in planning engineer work. The course gives you practical evidence of the skill; it does not promise a job, and employers decide on experience and interview.
All course factsHide course facts
- Price
- ₹0, free for good. No trial, no card. Comparable classroom training of this length costs about ₹5,999.
- Who it is for
- Civil, mechanical and electrical engineers moving into planning and project controls, site engineers who update programmes, and graduates seeking planning engineer roles on construction, oil and gas, water and power projects
- Format
- 14 self-paced modules, 10h 25m of video, written notes, a practice task per module and one final assessment.
- Level
- Beginner. Beginner to intermediate. For civil, mechanical and electrical engineers moving into planning and project controls, and site engineers asked to update the programme. Basic arithmetic and a spreadsheet are enough; no planning experience is needed. Project Management for Engineers covers the wider project management theory and is a good companion.
- Brand
- Vendor-neutral
- Software
- Oracle Primavera P6 Professional if your employer or college licenses it. Oracle has no free edition, and a trial, where Oracle offers one, is for evaluation (read its terms), so every exercise can also be done in ProjectLibre, which is free and open source, or by hand in a spreadsheet.
- Hardware
- A 64-bit Windows PC for P6 Professional (Oracle's list names Windows 11; check the tested configurations for your release). Oracle's stated minimum is 4 GB of memory and 5 GB of disk. ProjectLibre also runs on macOS and Linux.
- Certificate
- Optional EDWartens Certificate of Completion, ₹499 inclusive of GST for learners in India, verifiable by code. Not a vendor credential.
- Video lessons by
- TechnoCivil, Phil Hirst, Plan Academy Inc., Global Project Control, Engineer4Free, Obalim | Ciel Consulting, Claims Village, Learn with EngrWaqas (independent creators, credited below)
- Language
- English
- Last updated
- 1 November 2026
Pairs well with
PLC programming · FreeSiemens TIA Portal
PLC programming · FreeSiemens TIA Portal in Three Hours
PLC programming · FreeTIA Portal: Build a Machine
Instrumentation · FreeInstrumentation for PLC EngineersMore free courses: Free project management courses · Free civil engineering courses
Classroom course, Bangalore
PLC training in Bangalore
The Automation Engineer Program (AEP) is our classroom course in PLC programming and industrial automation, taught in person at our Electronic City centre.
Credits
Who made the video lessons
The video lessons in this course were created by the people below, not by EDWartens. Every lesson streams from its creator's own YouTube channel; EDWartens neither hosts nor sells that footage, and the creators are not affiliated with EDWartens and do not endorse this course. What EDWartens wrote is the study plan, the notes, the practice tasks and the assessments.
- TechnoCivilthe 25 lessons of the Primavera P6 series used across the course: EPS and OBS, admin categories and preferences, new projects, calendars, the WBS, activities and their settings, duration types, activity codes, relationships and constraints, printing, roles and resources, resource histograms, expenses and cost accounts, baselines, progress updating, earned value, and XER export and import
- Phil Hirstthe beginner and intermediate P6 tutorials on the workspace, the EPS and a new project, calendars, the WBS and activities, schedule logic and layouts, filters, grouping and baselines, and importing and resources
- Plan Academy Inc.CPM scheduling in P6 (also the recap in the final module), how calendars affect durations, the four relationship types, finding loops, defining critical activities, the longest path, float paths, cost-loading a fixed bid, indirects and overheads, an earned value layout, and earned schedule
- Global Project Controlnear-critical activities, resource levelling, the activity usage spreadsheet and profile, financial periods, baseline settings, out-of-sequence progress, and the schedule log
- Engineer4Freethe forward and backward pass, the critical path, and total and free float worked by hand
- Obalim | Ciel Consultingthe DCMA 14-point schedule check in P6, and fragnets and time impact analysis step by step
- Claims Villagethe introduction to the Society of Construction Law Delay and Disruption Protocol
- Learn with EngrWaqasdelay analysis and claims management with a windows analysis in Primavera P6
If you are one of these creators and would like a lesson removed or credited differently, write to info@edwartens.co.in.